Gulf Turbine ServicesExec◂ Apps

ExxonMobil Baytown — Cogen GT Inspection

GTS-2024-014CLOSED 6/6/2024
Edit
Added Jul 8, 2026Completed May 18, 2024
Company
Gulf Turbine Services
Client
Bayou Cogen
Source
MANUAL
Contract Type
T AND M
Market Segment
GT_OUTAGE
Public/Private
PRIVATE
Project Manager
Ray Daniels
Estimator
Phil Carter
Superintendent
Joe Tibbetts
Location
Baytown, TX

Margin Analysis

Original Margin
17.0%
$217,600
Revised Margin
18.0%
$257,600
Final Margin
18.0%
$257,600
Margin Gain (Bid)
+1.0%
CO Impact
$40,000
Margin Gain (Revised)
+0.0%

Where They Land

Final Margin+18.0%
Break Even
-0.9%+24.4%
Gain / Fade+0.0%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$1,280,000$1,062,400$217,60017.0%
Revised$1,430,000$1,172,400$257,60018.0%
Final$1,430,000$1,172,400$257,60018.0%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$341,889$424,528$430,896+$6,368+1.5%
Material$274,286$362,828$351,943$-10,885-3.0%
Subcontractor$263,094$291,595$292,168+$573+0.2%
Equipment$74,583$105,179$106,126+$947+0.9%
Other$108,547$35,172$31,655$-3,517-10.0%

Labor Productivity

Original Rate
$56/hr
Revised Rate
$68/hr
Final Rate
$73/hr
Hours Variance
-202
Rate Variance $
$100,319
Volume Variance $
$-11,312

Lessons Learned

What hurt

Refinery cogen access/permitting was the long pole, not the turbine work.

Client feedback

Bayou's EHS team praised our permit-readiness; it smoothed the next mobilization.

Assumptions / what to do differently

Build the safety/permit hours into the bid explicitly on refinery cogen sites — they're real and billable.

COGENPERMITTINGSAFETY HOURS