Mark VIe Controls Upgrade — 2x 7FA

GTS-2023-008CLOSED 8/25/2023
Edit
Added Jul 8, 2026Completed Mar 5, 2023
Company
Gulf Turbine Services
Client
Bayou Cogen
Source
MANUAL
Contract Type
LUMP SUM
Market Segment
IC_AND_E
Public/Private
PRIVATE
Project Manager
Dana Wright
Estimator
Susan Vance
Superintendent
Tariq Nolan
Location
Pasadena, TX
End User
Gulf Coast hyperscale data center (behind-the-meter offtaker)

Margin Analysis

Original Margin
16.0%
$264,000
Revised Margin
16.0%
$284,000
Final Margin
15.2%
$269,140
Margin Fade (Bid)
-0.8%
CO Impact
$20,000
Margin Fade (Revised)
-0.8%

Where They Land

Final Margin+15.2%
Break Even
-0.9%+24.4%
Gain / Fade-0.8%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$1,650,000$1,386,000$264,00016.0%
Revised$1,770,000$1,486,000$284,00016.0%
Final$1,770,000$1,500,860$269,14015.2%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$493,458$561,595$572,827+$11,232+2.0%
Material$369,885$401,988$393,948$-8,040-2.0%
Subcontractor$312,113$367,857$376,311+$8,454+2.3%
Equipment$137,308$131,593$133,172+$1,579+1.2%
Other$73,236$44,580$40,122$-4,458-10.0%

Labor Productivity

Original Rate
$62/hr
Revised Rate
$59/hr
Final Rate
$58/hr
Hours Variance
1,917
Rate Variance $
$-39,485
Volume Variance $
$118,854

Lessons Learned

What helped

Controls retrofits are a good margin lane and pull through outage work; the commissioning checklist kept us out of rework.

Client feedback

Bayou's hyperscale offtaker cared most about uptime risk during cutover — zero unplanned trips landed us the follow-on.

Assumptions / what to do differently

On behind-the-meter data-center cogen, plan the controls cutover around the offtaker's uptime windows, not just the plant's.

IC&ECONTROLSDATA CENTERUPTIME