Sandow — Steam Path Audit + Repair

GTS-2023-022CLOSED 12/2/2023
Edit
Added Jul 8, 2026Completed Feb 17, 2023
Company
Gulf Turbine Services
Client
Riverbend Energy
Source
MANUAL
Contract Type
UNIT PRICE
Market Segment
STEAM_OVERHAUL
Public/Private
PRIVATE
Project Manager
Dana Wright
Estimator
Phil Carter
Superintendent
Marcus Hill
Location
Rockdale, TX

Margin Analysis

Original Margin
12.0%
$288,000
Revised Margin
11.2%
$308,000
Final Margin
8.5%
$234,740
Margin Fade (Bid)
-3.5%
CO Impact
$20,000
Margin Fade (Revised)
-2.7%

Where They Land

Final Margin+8.5%
Break Even
-0.9%+24.4%
Gain / Fade-2.7%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$2,400,000$2,112,000$288,00012.0%
Revised$2,750,000$2,442,000$308,00011.2%
Final$2,750,000$2,515,260$234,7408.5%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$737,889$885,402$934,099+$48,697+5.5%
Material$560,373$626,030$629,160+$3,130+0.5%
Subcontractor$619,898$587,008$603,746+$16,738+2.9%
Equipment$189,982$233,192$240,887+$7,695+3.3%
Other$63,360$110,368$107,368$-3,000-2.7%

Labor Productivity

Original Rate
$65/hr
Revised Rate
$66/hr
Final Rate
$60/hr
Hours Variance
4,216
Rate Variance $
$-77,833
Volume Variance $
$274,043