Gulf Turbine ServicesExec◂ Apps

Outage Standby — Peaking Fleet

GTS-2024-012
EditClose Project
Added Jul 8, 2026Completed Feb 3, 2024
Company
Gulf Turbine Services
Client
Gulf Power
Source
MANUAL
Contract Type
T AND M
Market Segment
FIELD_SERVICE
Public/Private
PUBLIC
Project Manager
Dana Wright
Estimator
Susan Vance
Superintendent
Carl Boudreaux
Location
Austin, TX

Margin Analysis

Original Margin
19.0%
$102,600
Revised Margin
20.4%
$132,600
Final Margin
20.0%
$130,013
Margin Gain (Bid)
+1.0%
CO Impact
$30,000
Margin Fade (Revised)
-0.4%

Where They Land

Final Margin+20.0%
Break Even
-0.9%+24.4%
Gain / Fade-0.4%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$540,000$437,400$102,60019.0%
Revised$650,000$517,400$132,60020.4%
Final$650,000$519,987$130,01320.0%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$170,496$182,531$184,356+$1,825+1.0%
Material$116,922$140,162$138,760$-1,402-1.0%
Subcontractor$130,252$117,017$116,388$-629-0.5%
Equipment$27,716$38,653$38,885+$232+0.6%
Other$13,122$39,037$41,598+$2,561+6.6%

Labor Productivity

Original Rate
$78/hr
Revised Rate
$72/hr
Final Rate
$82/hr
Hours Variance
62
Rate Variance $
$9,024
Volume Variance $
$4,836

Notes

Seasonal standby. Reliable margin, builds the relationship.