Gulf Turbine ServicesExec◂ Apps

7EA Compressor Rotor — Restack

GTS-2024-009
EditClose Project
Added Jul 8, 2026Completed Jun 15, 2024
Company
Gulf Turbine Services
Client
Delta Energy
Source
MANUAL
Contract Type
COST PLUS
Market Segment
SHOP_OVERHAUL
Public/Private
PUBLIC
Project Manager
Dana Wright
Estimator
Susan Vance
Superintendent
Eddie Rangel
Location
Houston, TX
End User
Riverside Generating Station (asset owner)

Margin Analysis

Original Margin
16.0%
$448,000
Revised Margin
15.7%
$488,000
Final Margin
15.3%
$474,940
Margin Fade (Bid)
-0.7%
CO Impact
$40,000
Margin Fade (Revised)
-0.4%

Where They Land

Final Margin+15.3%
Break Even
-0.9%+24.4%
Gain / Fade-0.4%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$2,800,000$2,352,000$448,00016.0%
Revised$3,100,000$2,612,000$488,00015.7%
Final$3,100,000$2,625,060$474,94015.3%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$837,503$880,226$893,429+$13,203+1.5%
Material$699,375$785,329$765,696$-19,633-2.5%
Subcontractor$582,897$670,087$684,180+$14,093+2.1%
Equipment$218,272$207,449$209,316+$1,867+0.9%
Other$70,560$78,360$72,439$-5,921-7.6%

Labor Productivity

Original Rate
$61/hr
Revised Rate
$81/hr
Final Rate
$73/hr
Hours Variance
-1,491
Rate Variance $
$146,874
Volume Variance $
$-90,948

Notes

Cost-plus on a complex restack protected margin through scope discovery.