Gulf Turbine ServicesExec◂ Apps

501F Transition Pieces — Repair

GTS-2023-017CLOSED 11/5/2023
Edit
Added Jul 8, 2026Completed Oct 16, 2023
Company
Gulf Turbine Services
Client
Delta Energy
Source
MANUAL
Contract Type
LUMP SUM
Market Segment
SHOP_OVERHAUL
Public/Private
PUBLIC
Project Manager
Dana Wright
Estimator
Phil Carter
Superintendent
Eddie Rangel
Location
Houston, TX

Margin Analysis

Original Margin
17.0%
$229,500
Revised Margin
15.4%
$214,500
Final Margin
14.6%
$202,745
Margin Fade (Bid)
-2.4%
CO Impact
$-15,000
Margin Fade (Revised)
-0.8%

Where They Land

Final Margin+14.6%
Break Even
-0.9%+24.4%
Gain / Fade-0.8%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$1,350,000$1,120,500$229,50017.0%
Revised$1,390,000$1,175,500$214,50015.4%
Final$1,390,000$1,187,255$202,74514.6%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$368,899$463,635$475,226+$11,591+2.5%
Material$323,278$342,592$332,314$-10,278-3.0%
Subcontractor$291,296$286,628$288,286+$1,658+0.6%
Equipment$109,950$78,800$79,982+$1,182+1.5%
Other$33,615$35,265$31,739$-3,526-10.0%

Labor Productivity

Original Rate
$80/hr
Revised Rate
$60/hr
Final Rate
$76/hr
Hours Variance
1,642
Rate Variance $
$-25,040
Volume Variance $
$131,367