7FA R1 Bucket Set — Shop Overhaul

GTS-2023-002CLOSED 6/21/2023
Edit
Added Jul 8, 2026Completed Nov 11, 2023
Company
Gulf Turbine Services
Client
Delta Energy
Source
MANUAL
Contract Type
LUMP SUM
Market Segment
SHOP_OVERHAUL
Public/Private
PRIVATE
Project Manager
Dana Wright
Estimator
Phil Carter
Superintendent
Eddie Rangel
Location
Houston, TX

Margin Analysis

Original Margin
18.0%
$378,000
Revised Margin
18.9%
$408,000
Final Margin
20.9%
$451,800
Margin Gain (Bid)
+2.9%
CO Impact
$30,000
Margin Gain (Revised)
+2.0%

Where They Land

Final Margin+20.9%
Break Even
-0.9%+24.4%
Gain / Fade+2.0%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$2,100,000$1,722,000$378,00018.0%
Revised$2,160,000$1,752,000$408,00018.9%
Final$2,160,000$1,708,200$451,80020.9%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$620,084$573,620$567,884$-5,736-1.0%
Material$485,714$527,027$500,676$-26,351-5.0%
Subcontractor$411,857$428,489$430,700+$2,211+0.5%
Equipment$135,180$155,907$154,972$-935-0.6%
Other$69,166$66,957$60,261$-6,696-10.0%

Labor Productivity

Original Rate
$66/hr
Revised Rate
$72/hr
Final Rate
$69/hr
Hours Variance
-1,165
Rate Variance $
$24,692
Volume Variance $
$-76,892

Lessons Learned

What helped

Shop work is where the margin lives — predictable, our bench, our process. Coating vendor came in under quote.

Client feedback

Delta now defaults the bucket sets to our shop.

SHOPVENDORREPEAT BUSINESS