DeCordova — 7EA Major Outage

GTS-2024-003
EditClose Project
Added Jul 8, 2026Completed Aug 21, 2024
Company
Gulf Turbine Services
Client
Lone Star Power
Source
MANUAL
Contract Type
UNIT PRICE
Market Segment
GT_OUTAGE
Public/Private
PRIVATE
Project Manager
Ray Daniels
Estimator
Susan Vance
Superintendent
Marcus Hill
Location
Granbury, TX

Margin Analysis

Original Margin
12.0%
$468,000
Revised Margin
11.7%
$518,000
Final Margin
7.3%
$322,900
Margin Fade (Bid)
-4.7%
CO Impact
$50,000
Margin Fade (Revised)
-4.4%

Where They Land

Final Margin+7.3%
Break Even
-0.9%+24.4%
Gain / Fade-4.4%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$3,900,000$3,432,000$468,00012.0%
Revised$4,420,000$3,902,000$518,00011.7%
Final$4,420,000$4,097,100$322,9007.3%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$1,269,804$1,529,807$1,675,139+$145,332+9.5%
Material$922,703$1,088,319$1,131,852+$43,533+4.0%
Subcontractor$882,758$1,112,730$1,131,227+$18,497+1.7%
Equipment$341,132$328,855$347,600+$18,745+5.7%
Other$102,960$117,060$105,354$-11,706-10.0%

Labor Productivity

Original Rate
$64/hr
Revised Rate
$59/hr
Final Rate
$60/hr
Hours Variance
8,078
Rate Variance $
$-111,649
Volume Variance $
$516,984

Notes

Unit-price recovered most CO scope. Rotor found needing more than planned.