Mark VIe Controls Upgrade — 2x 7FA

GTS-2023-008CLOSED 8/11/2023
Edit
Added Jun 18, 2026Completed Jan 26, 2023
Company
Gulf Turbine Services
Client
Calpine
Source
MANUAL
Contract Type
LUMP SUM
Market Segment
IC_AND_E
Public/Private
PRIVATE
Project Manager
Dana Wright
Estimator
Susan Vance
Superintendent
Tariq Nolan
Location
Pasadena, TX

Margin Analysis

Original Margin
16.0%
$264,000
Revised Margin
16.0%
$284,000
Final Margin
15.2%
$269,140
Margin Fade (Bid)
-0.8%
CO Impact
$20,000
Margin Fade (Revised)
-0.8%

Where They Land

Final Margin+15.2%
Break Even
-0.9%+24.4%
Gain / Fade-0.8%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$1,650,000$1,386,000$264,00016.0%
Revised$1,770,000$1,486,000$284,00016.0%
Final$1,770,000$1,500,860$269,14015.2%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$455,593$570,456$581,865+$11,409+2.0%
Material$384,553$378,045$370,484$-7,561-2.0%
Subcontractor$351,184$436,963$443,420+$6,457+1.5%
Equipment$120,825$130,347$131,911+$1,564+1.2%
Other$73,845$44,580$40,122$-4,458-10.0%

Labor Productivity

Original Rate
$59/hr
Revised Rate
$75/hr
Final Rate
$78/hr
Hours Variance
-262
Rate Variance $
$141,730
Volume Variance $
$-15,458

Lessons Learned

Controls retrofits are a good margin lane and pull through outage work. Tariq's commissioning checklist kept us out of rework.