Limestone U1 — Steam Turbine Major

GTS-2022-016CLOSED 12/11/2022
Edit
Added Jun 18, 2026Completed Mar 20, 2022
Company
Gulf Turbine Services
Client
NRG Energy
Source
MANUAL
Contract Type
LUMP SUM
Market Segment
STEAM_OVERHAUL
Public/Private
PRIVATE
Project Manager
Ray Daniels
Estimator
Phil Carter
Superintendent
Marcus Hill
Location
Jewett, TX

Margin Analysis

Original Margin
11.0%
$451,000
Revised Margin
7.0%
$331,000
Final Margin
-0.9%
$-40,365
Margin Fade (Bid)
-11.9%
CO Impact
$-120,000
Margin Fade (Revised)
-7.9%

Where They Land

Final Margin-0.9%
Break Even
-0.9%+24.4%
Gain / Fade-7.9%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$4,100,000$3,649,000$451,00011.0%
Revised$4,700,000$4,369,000$331,0007.0%
Final$4,700,000$4,740,365$-40,365-0.9%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$1,416,625$1,620,199$1,847,027+$226,828+14.0%
Material$963,243$1,334,779$1,361,475+$26,696+2.0%
Subcontractor$991,747$984,208$997,914+$13,706+1.4%
Equipment$258,818$436,895$473,594+$36,699+8.4%
Other$109,470$131,070$117,963$-13,107-10.0%

Labor Productivity

Original Rate
$79/hr
Revised Rate
$77/hr
Final Rate
$60/hr
Hours Variance
12,852
Rate Variance $
$-584,904
Volume Variance $
$1,015,306

Lessons Learned

Steam majors are our hardest fade. The LP last-stage blades found more erosion than scoped. We under-price steam labor — it needs a different productivity factor than GT.