7FA Combustion Tuning Campaign

GTS-2023-019CLOSED 10/20/2023
Edit
Added Jun 18, 2026Completed Jul 19, 2023
Company
Gulf Turbine Services
Client
NextEra Energy
Source
MANUAL
Contract Type
T AND M
Market Segment
FIELD_SERVICE
Public/Private
PRIVATE
Project Manager
Ray Daniels
Estimator
Susan Vance
Superintendent
Carl Boudreaux
Location
Mont Belvieu, TX

Margin Analysis

Original Margin
21.0%
$100,800
Revised Margin
22.9%
$125,800
Final Margin
24.4%
$134,284
Margin Gain (Bid)
+3.4%
CO Impact
$25,000
Margin Gain (Revised)
+1.5%

Where They Land

Final Margin+24.4%
Break Even
-0.9%+24.4%
Gain / Fade+1.5%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$480,000$379,200$100,80021.0%
Revised$550,000$424,200$125,80022.9%
Final$550,000$415,716$134,28424.4%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$150,174$157,499$155,924$-1,575-1.0%
Material$115,198$111,062$109,396$-1,666-1.5%
Subcontractor$109,350$117,321$117,100$-221-0.2%
Equipment$24,918$40,373$40,131$-242-0.6%
Other$11,376$12,726$11,453$-1,273-10.0%

Labor Productivity

Original Rate
$68/hr
Revised Rate
$75/hr
Final Rate
$74/hr
Hours Variance
-101
Rate Variance $
$12,619
Volume Variance $
$-6,869