7EA Compressor Rotor — Restack

GTS-2024-009
EditClose Project
Added Jun 18, 2026Completed Nov 3, 2024
Company
Gulf Turbine Services
Client
Brazos Electric
Source
MANUAL
Contract Type
COST PLUS
Market Segment
SHOP_OVERHAUL
Public/Private
PUBLIC
Project Manager
Dana Wright
Estimator
Susan Vance
Superintendent
Eddie Rangel
Location
Houston, TX

Margin Analysis

Original Margin
16.0%
$448,000
Revised Margin
15.7%
$488,000
Final Margin
15.3%
$474,940
Margin Fade (Bid)
-0.7%
CO Impact
$40,000
Margin Fade (Revised)
-0.4%

Where They Land

Final Margin+15.3%
Break Even
-0.9%+24.4%
Gain / Fade-0.4%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$2,800,000$2,352,000$448,00016.0%
Revised$3,100,000$2,612,000$488,00015.7%
Final$3,100,000$2,625,060$474,94015.3%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$807,091$1,004,475$1,019,542+$15,067+1.5%
Material$678,255$709,801$692,056$-17,745-2.5%
Subcontractor$596,321$608,431$617,727+$9,296+1.5%
Equipment$168,480$208,061$209,934+$1,873+0.9%
Other$101,852$81,232$85,801+$4,569+5.6%

Labor Productivity

Original Rate
$85/hr
Revised Rate
$77/hr
Final Rate
$75/hr
Hours Variance
4,099
Rate Variance $
$-135,971
Volume Variance $
$348,422

Notes

Cost-plus on a complex restack protected margin through scope discovery.