◂ AppsGTS Exec SuiteGTS Exec

7FA R1 Bucket Set — Shop Overhaul

GTS-2023-002CLOSED 6/17/2023
Edit
Added Jun 18, 2026Completed May 23, 2023
Company
Gulf Turbine Services
Client
Calpine
Source
MANUAL
Contract Type
LUMP SUM
Market Segment
SHOP_OVERHAUL
Public/Private
PRIVATE
Project Manager
Dana Wright
Estimator
Phil Carter
Superintendent
Eddie Rangel
Location
Houston, TX

Margin Analysis

Original Margin
18.0%
$378,000
Revised Margin
18.9%
$408,000
Final Margin
20.9%
$451,800
Margin Gain (Bid)
+2.9%
CO Impact
$30,000
Margin Gain (Revised)
+2.0%

Where They Land

Final Margin+20.9%
Break Even
-0.9%+24.4%
Gain / Fade+2.0%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$2,100,000$1,722,000$378,00018.0%
Revised$2,160,000$1,752,000$408,00018.9%
Final$2,160,000$1,708,200$451,80020.9%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$578,722$586,327$580,464$-5,863-1.0%
Material$529,234$475,536$451,759$-23,777-5.0%
Subcontractor$484,412$426,675$423,496$-3,179-0.7%
Equipment$171,549$129,834$129,055$-779-0.6%
Other$51,660$133,628$123,426$-10,202-7.6%

Labor Productivity

Original Rate
$63/hr
Revised Rate
$58/hr
Final Rate
$62/hr
Hours Variance
176
Rate Variance $
$-9,346
Volume Variance $
$11,088

Lessons Learned

Shop work is where our margin lives. Predictable, our bench, our process. Coating vendor came in under quote.