S.R. Bertron — Forced Outage Support

GTS-2022-021CLOSED 9/6/2022
Edit
Added Jun 18, 2026Completed Sep 8, 2022
Company
Gulf Turbine Services
Client
NRG Energy
Source
MANUAL
Contract Type
T AND M
Market Segment
GT_OUTAGE
Public/Private
PRIVATE
Project Manager
Dana Wright
Estimator
Susan Vance
Superintendent
Joe Tibbetts
Location
Deer Park, TX

Margin Analysis

Original Margin
22.0%
$215,600
Revised Margin
22.6%
$275,600
Final Margin
21.0%
$256,712
Margin Fade (Bid)
-1.0%
CO Impact
$60,000
Margin Fade (Revised)
-1.5%

Where They Land

Final Margin+21.0%
Break Even
-0.9%+24.4%
Gain / Fade-1.5%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$980,000$764,400$215,60022.0%
Revised$1,220,000$944,400$275,60022.6%
Final$1,220,000$963,288$256,71221.0%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$295,488$317,140$329,826+$12,686+4.0%
Material$193,348$288,533$285,648$-2,885-1.0%
Subcontractor$223,071$280,463$287,661+$7,198+2.6%
Equipment$68,522$92,430$94,648+$2,218+2.4%
Other$22,932$28,332$25,499$-2,833-10.0%

Labor Productivity

Original Rate
$65/hr
Revised Rate
$74/hr
Final Rate
$59/hr
Hours Variance
1,044
Rate Variance $
$-33,522
Volume Variance $
$67,860

Lessons Learned

Forced-outage premium work prints margin when we're the ones who can mobilize in 24h. Keep a standby crew costed in.