Wolf Hollow II — 7FA Combustion Inspection

GTS-2023-011CLOSED 7/6/2023
Edit
Added Jun 18, 2026Completed Aug 22, 2023
Company
Gulf Turbine Services
Client
Talen Energy
Source
MANUAL
Contract Type
T AND M
Market Segment
GT_OUTAGE
Public/Private
PRIVATE
Project Manager
Dana Wright
Estimator
Phil Carter
Superintendent
Joe Tibbetts
Location
Granbury, TX

Margin Analysis

Original Margin
15.0%
$217,500
Revised Margin
15.8%
$247,500
Final Margin
14.5%
$227,663
Margin Fade (Bid)
-0.5%
CO Impact
$30,000
Margin Fade (Revised)
-1.3%

Where They Land

Final Margin+14.5%
Break Even
-0.9%+24.4%
Gain / Fade-1.3%
As Predicted
-7.9%+2.0%
This project
Other projects
Zero reference

Revenue & Cost Summary

StageRevenueCostProfitMargin
Original$1,450,000$1,232,500$217,50015.0%
Revised$1,570,000$1,322,500$247,50015.8%
Final$1,570,000$1,342,337$227,66314.5%

Cost Category Variance

CategoryOriginalRevisedFinalVariance $Over/Under %
Labor$474,310$475,367$489,628+$14,261+3.0%
Material$338,593$339,858$333,061$-6,797-2.0%
Subcontractor$310,842$293,106$294,688+$1,582+0.5%
Equipment$77,319$112,518$114,543+$2,025+1.8%
Other$36,975$101,652$110,417+$8,765+8.6%

Labor Productivity

Original Rate
$58/hr
Revised Rate
$56/hr
Final Rate
$66/hr
Hours Variance
-759
Rate Variance $
$59,339
Volume Variance $
$-44,021

Lessons Learned

Clean CI, T&M protected us. Joe's crew turned it in 9 days. This is the model outage.